The Zambia Public Procurement Authority (ZPPA) has suspended three contractors from participating in public procurement for two years following their failure to fulfil contractual obligations under borehole drilling and rehabilitation projects.
The suspended companies are Capricon Innovation Limited, Nkanmu Investments Limited and Totten Infrastructure Limited, which were contracted by the Ministry of Water Development and Sanitation to undertake borehole works in various provinces.
ZPPA Director General Gloria Ngoma says investigations established that the contractors failed to complete the assigned works despite receiving advance payments.
Ms. Ngoma says Capricon Innovation Limited failed to drill and equip boreholes in four provinces, despite having been paid a 25 % advanced payment amounting to K8, 220, 804.7, while Nkanmu Investments Limited rehabilitated only 11 out of 95 boreholes in Western Province despite having been a 25% advance payment amounting to K1, 255, 009.45
On the other hand, Totten Infrastructure Limited also abandoned rehabilitation works in Muchinga Province after dismantling existing boreholes that had been supplying water to communities despite having been an advanced payment of K98, 430.64.
The suspensions took effect on July 14, 2026.
ZPPA has since directed the Ministry to recover the advance payments made to the three companies through the Office of the Attorney General.
Meanwhile, the Authority has flagged irregular contract extensions, poor record management, inadequate documentation and construction defects in 26 CDF projects monitored across 11 local authorities.
The concerns follow the monitoring of 26 CDF projects in 11 local authorities across the education, health, water, sanitation and public infrastructure sectors.